DESIGN WORKING GROUP MEETING 24-06-2026
Meeting Summary
Date: 24 June 2026
Duration: 1 Hour 28 Minutes
Meeting Objective
The meeting focused on sharing practical lessons learned from delivering a High-Risk Building (HRB) remediation project under the Building Safety Act. Discussions covered Gateway 2 submissions, compliance documentation, design coordination, change management, as-built information, and best practices for obtaining Building Safety Regulator (BSR) approval.
Key Discussion Points
- HRB Remediation Project Overview
Andrew de Silva presented a live remediation project involving partial façade replacement on an occupied High-Risk Building.
The project team was responsible for:
- Building Safety Architect
- Acting BIM Lead
- Principal Designer (CDM)
- Building Safety Advisor
The presentation highlighted how Gateway 2 projects require significantly greater planning, coordination, and documentation compared with traditional construction projects.
- Gateway 2 Submission Strategy
A key recommendation was to treat Gateway 2 as a Building Control compliance submission rather than a full construction drawing package.
The submission should:
- Demonstrate compliance with applicable Building Regulations.
- Include only information relevant to the proposed building works.
- Avoid unnecessary construction details.
- Clearly explain how compliance has been achieved.
This approach creates a focused submission while reducing unnecessary documentation.
- Design Coordination with Specialist Manufacturers
The project required close collaboration with specialist manufacturers and subcontractors throughout the design process.
The design team carefully reviewed:
- Fire certification
- Declaration of Performance (DoP)
- Field of Application documents
- Product compatibility
- Manufacturer approvals
Every construction detail was coordinated and agreed before submission to ensure that the approved design accurately reflected the intended construction.
- Managing As-Built Information
A significant discussion focused on defining "As-Built" information under the new Building Safety regulations.
Key conclusions included:
- Gateway 2 drawings represent the approved design intent.
- Any design changes during construction must follow the formal change management process.
- Principal Contractors are responsible for confirming that the completed works comply with the approved design.
- Designers should only update drawings based on documented and verified changes.
- Maintaining a complete audit trail is essential for future compliance and asset management.
- Compliance Statement
Andrew demonstrated the structure of the Compliance Statement prepared for the Gateway 2 submission.
The document includes:
- Description of the proposed building work.
- Identification of applicable Building Regulations.
- Justification for each regulation that applies.
- Explanation of regulations that are not applicable.
- References to supporting drawings, reports, certifications, and technical documents.
The emphasis was on answering exactly what the legislation requires rather than producing unnecessary documentation.
- Fire and Emergency File
Another important submission document discussed was the Fire and Emergency File.
The document explains:
- How the proposed works affect fire spread.
- Structural implications of the design.
- Building safety measures introduced.
- Impacts on occupants and accountable persons.
- Information relevant to emergency services.
Rather than reproducing an entire Fire Strategy, the document focuses specifically on the impact of the proposed works.
- Working Directly from Legislation
One of the strongest recommendations was to base submissions directly on the wording of the legislation.
The team advised:
- Read the legislation itself rather than relying only on guidance.
- Answer the legal requirements exactly as written.
- Clearly explain why regulations are applicable or not applicable.
- Avoid adding unnecessary information that does not support compliance.
- Change Management
Participants agreed that change management remains one of the weakest areas across construction projects.
Best practices discussed included:
- Recording every design change, regardless of size.
- Maintaining a complete audit trail.
- Documenting specialist contractor modifications.
- Managing changes through the Common Data Environment (CDE).
- Using formal approval procedures before updating drawings.
- Industry Experience and Lessons Learned
Participants shared practical experience from multiple Gateway 2 submissions.
Key lessons included:
- Focus on answering the regulator's questions rather than producing excessive documentation.
- Clearly document temporary construction arrangements for occupied buildings.
- Anticipate foreseeable changes within the Change Control Plan.
- Support submissions with clear evidence and references.
- Engage specialist contractors early to improve coordination and compliance.
Best Practice Recommendations
- Treat Gateway 2 as a compliance submission rather than a construction package.
- Base every submission directly on legislative requirements.
- Involve specialist manufacturers and subcontractors early.
- Produce concise but well-supported Compliance Statements and Fire & Emergency Files.
- Maintain strict change control procedures throughout the project.
- Ensure as-built information accurately reflects approved changes.
- Keep a complete audit trail throughout design and construction.
- Continue sharing lessons learned across BIM4Housing working groups.
Key Takeaways
The meeting demonstrated that successful Gateway 2 submissions rely on clear compliance evidence, strong multidisciplinary coordination, disciplined change management, and accurate documentation rather than simply producing more drawings. Early involvement of specialist contractors, a structured compliance approach, and maintaining an auditable record throughout the project lifecycle are essential for achieving regulatory approval and improving long-term building safety.